Hello, you are using an old browser that's unsafe and no longer supported. Please consider updating your browser to a newer version, or downloading a modern browser.
Daniel J. Keating was selected as the general contractor for the rehabilitation of the SEPTA Airport Platform. The improvements planned as part of this project will enhance the travel experience for the millions of visitors who fly to Philadelphia each year for tourism and business.
Overall Cost / $12,000,000
Owner / South Eastern Pennsylvania Transportation Authority (SEPTA)
Architect / TransSystems
Project Status / Anticipated completion date of Spring 2024.
The improvements will include concrete restoration, new roofing on all center platforms, new polycarbonate panels, new ACM panels, new curtain walls and doors, and fresh paint on concrete walls and columns.